← All playbooks
Project management migration

Trello → Asana

Move Trello boards and cards into Asana projects and tasks while accounting for the CSV path’s loss of comments, activity, Power-Ups, automation, permissions, and board behavior.

Typical timeline6–12 business days22–40 hours active work
Statusneeds review
Source testedTrello documentation reviewed 2026-07-19
Destination testedAsana documentation reviewed 2026-07-19
Last reviewed2026-07-19
Sources3
Before you migrate

Should you make this move?

Both platforms have a case. Compare what you gain with what you give up before scheduling the cutover.

Current platform

Trello

Reasons to stay
  • Visual boards are immediately understandable and require almost no training
  • Structured ownership, status, and workflow views improve operational visibility
Reasons to leave
  • Dependencies, planning depth, reporting, and scale expose its simplicity
  • Custom fields, automations, history, and reporting are difficult to reproduce exactly
New platform

Asana

What gets better
  • Flexible project planning serves many departments and work styles
  • Structured ownership, status, and workflow views improve operational visibility
What gets worse
  • Broad flexibility can produce inconsistent structures and administrative sprawl
  • Custom fields, automations, history, and reporting are difficult to reproduce exactly
Best of the move

Asana: Flexible project planning serves many departments and work styles. This removes a major source-side concern: Dependencies, planning depth, reporting, and scale expose its simplicity.

Worst of the move

What you lose: Visual boards are immediately understandable and require almost no training. What you inherit: Broad flexibility can produce inconsistent structures and administrative sprawl.

01At a glance

Know the shape of the move.

Transfer outcome12 features audited
Transfer outcome distributionClean transfer: 0, Partial transfer: 10, Manual rebuild: 0, Not transferred: 2.
Clean0
Partial10
Manual0
Lost2
Mapping route9 of 9 fields have a destination path

This timeline assumes

  • Up to 100 boards, 20,000 cards, and 100 members
  • Only active work and explicitly approved history enter the destination.
  • Users and guests are provisioned before assignment mapping.
  • A representative project or board is imported before the full workspace.
  • The migration team records evidence for every blocking verification check.
02Loss matrix

What survives the move.

“Partial” and “manual” are not footnotes. They are work that must be scheduled and verified.

ItemOutcomeImpactWhat happensMitigation
Boards, lists, and cardspartialcriticalAsana imports Trello CSV rows into a project, but board semantics depend on how lists map to sections or status.Approve one mapping per board and pilot every workflow shape.
Comments, card activity, and archived historylosthighThe documented CSV route does not recreate Trello’s complete collaboration history.Keep JSON exports and copy critical decisions into task descriptions.
Checklists, attachments, covers, and custom fieldspartialhighCSV columns cannot reproduce every structured card feature or binary.Export attachments separately and define a deterministic checklist and field transformation.
Power-Ups, Butler automation, watchers, and permissionslostcriticalTrello runtime configuration is outside the CSV import.Rebuild required rules and test private-project access before cutover.
Projects, boards, and active workpartialcriticalCore work items can move, but source and destination hierarchy differ.Approve the destination hierarchy before importing tasks.
Task titles and descriptionspartialhighText transfers more reliably than rich blocks, embeds, and application-specific markup.Compare a stratified sample containing every content type.
Statuses, sections, and workflowpartialcriticalColumns, sections, groups, and statuses can represent different business concepts.Map each source value to one approved destination state.
Assignees, teams, and guestspartialcriticalUser identities can map while roles, guest scope, and licensing change.Provision users first and test internal and external access.
Dates, milestones, and dependenciespartialhighDue dates may move while schedules, dependency types, and baseline behavior differ.Rebuild critical dependencies and validate milestone ordering.
Comments and activity historypartialhighImport coverage and author attribution vary by route.Archive full history and verify every required collaboration type.
Attachments and external linkspartialhighFiles can exceed limits or remain linked to source-only URLs.Copy required binaries and test access as ordinary users.
Custom fields and calculated valuespartialhighField types, options, formulas, and validation do not match exactly.Create a signed field dictionary and preserve source values.
03Field and feature mapping

Where each thing goes.

SourceDestinationMethodNotes
Trello project or boardAsana project, team, or containertransformApprove hierarchy and ownership first.
Task or cardTask or issuetransformPreserve source ID and URL.
Section, list, group, or statusDestination status or groupingtransformMap business meaning, not visual position.
Assignee or memberDestination assigneemanualMap inactive and guest users explicitly.
Due date or milestoneDestination date or milestonetransformNormalize timezone and date-only values.
Dependency or relationDestination dependency or relationtransformCreate after both work items exist.
Custom fieldDestination field or labeltransformMap type, options, and null values.
Comment or updateDestination comment or archived contexttransformPreserve author and timestamp when supported.
AttachmentDestination attachment or durable linktransformCopy the binary and verify ordinary-user access.
04Before you begin

Make the move recoverable.

Backup procedure

Create the source-of-truth backup

Preserve Trello data, configuration, and operating evidence before any destination write.

  1. Export all available Trello projects, work items, comments, files, users, fields, and settings.
  2. Capture project structure, statuses, permissions, templates, automations, integrations, and active schedules.
  3. Record counts by project, state, owner, and item type.
  4. Hash raw exports and transform working copies only.

Proof to capture: A signed manifest reconciles every scoped record class, runtime dependency, export file, count, and hash.

Transformation · Migration workbook

Work hierarchy and state map

Preserve ownership and workflow meaning.

  1. Inventory source values and exceptions.
  2. Define explicit destination mappings.
  3. Reject unmapped critical records.

Proof to capture: Save the input, output, command or tool settings, warnings, and final item counts.

Transformation · CSV or API transformer

Destination import files

Create deterministic users, work items, fields, and relationships.

  1. Normalize encoding, dates, identifiers, and blanks.
  2. Run a representative pilot.
  3. Reconcile accepted, rejected, and transformed rows.

Proof to capture: Save the input, output, command or tool settings, warnings, and final item counts.

05Handle with care

The things most likely to hurt.

These are operating limits. Treat every “Stop if” condition as a blocked migration, not a suggestion.

Mapping

Hierarchy or status changes meaning

criticalpossible likelihood

Work appears in the wrong team, project, or workflow state.

Consequence
Teams lose ownership and act on the wrong priorities.
Mitigation
Approve mappings with project owners before bulk import.

Stop if: A critical state or owner has no deterministic destination.

Import

Private work becomes visible

criticalpossible likelihood

Imported containers inherit broader destination access.

Consequence
Confidential projects or client work is exposed.
Mitigation
Create and test access before inviting users.

Stop if: An unauthorized test user can open restricted work.

Cutover

Both tools create actions

criticalpossible likelihood

Source rules and destination automations both notify or update work.

Consequence
Tasks drift and people receive duplicate actions.
Mitigation
Freeze source automations and enable replacements one at a time.

Stop if: Any unapproved source writer remains active.

06Precise timeline

Do the work in this order.

Estimate forUp to 100 boards, 20,000 cards, and 100 members
Total elapsed6–12 business days
Active work22–40 hours
BufferAdd time for attachment-heavy boards, many custom fields, Butler rules, or cross-board dependencies.
01
Days 1–3Inventory and decisions2–3 days
02
Days 3–5Backup and reconcile1–3 days
03
Days 5–12Map and pilot3–8 days
04
Days 10–20Final delta and switch1–5 days
05
Days 12–40Observe and close3–10 days
  1. Days 1–3 · inventory

    Inventory and decisions

    6–12 hours active2–3 days elapsedOwner review waiting
    • Inventory Trello data, features, users, domains, and integrations.
    • Approve scope, owners, mappings, and exclusions.

    Depends on: Trello and Asana administrator access

    Stop / go checkpoint

    Export?

    Go when: Every critical item has an owner and disposition.

    Stop when: Consent, billing, access, or system ownership is unclear.

  2. Days 3–5 · backup

    Backup and reconcile

    5–10 hours active1–3 days elapsedExport processing waiting
    • Create immutable exports and configuration evidence.
    • Reconcile counts, totals, and hashes.

    Depends on: Approved inventory

    Stop / go checkpoint

    Transform?

    Go when: Source totals and export manifests agree.

    Stop when: Any critical dataset or configuration is absent.

  3. Days 5–12 · pilot

    Map and pilot

    10–35 hours active3–8 days elapsedDestination processing and review waiting
    • Configure Asana and transform representative data.
    • Run a pilot containing normal records and every critical edge case.

    Depends on: Verified backup

    Stop / go checkpoint

    Scale?

    Go when: Pilot mappings, behavior, access, and evidence pass.

    Stop when: Any critical check fails or produces unexplained variance.

  4. Days 10–20 · cutover

    Final delta and switch

    5–25 hours active1–5 days elapsedDNS, import, or sync propagation waiting
    • Freeze production writes in Trello.
    • Apply the final delta, switch ownership, and run blocking checks.

    Depends on: Passed pilot and approved rollback

    Stop / go checkpoint

    Open production?

    Go when: Counts reconcile and one destination system owns production.

    Stop when: A source writer remains active or a blocking check fails.

  5. Days 12–40 · observe

    Observe and close

    3–18 hours active3–10 days elapsedOperating-cycle evidence waiting
    • Monitor one complete operating cycle.
    • Sign the verification report and close rollback only after stability.

    Depends on: Verified cutover

    Stop / go checkpoint

    Close rollback?

    Go when: No trigger occurs during the agreed observation period.

    Stop when: Data, access, delivery, routing, or business results regress.

07The point of change

Cut over with a way back.

Go live

Cutover

Make Asana the only production system without losing the final Trello delta.

Recommended window: A low-volume weekday morning with platform, data, DNS, and business owners available.

  1. Freeze production writes and scheduled actions in Trello.
  2. Export, transform, and reconcile the final delta.
  3. Apply the approved delta to Asana.
  4. Switch domains, forms, integrations, sending, or sync ownership as applicable.
  5. Run every blocking verification check and keep the source intact.

Proof to capture: Asana owns production, totals reconcile, and every blocking check has durable evidence.

Return to safety

Rollback

Return production ownership to Trello without losing destination-era changes.

Deadline: Within seven days and before source data, plans, credentials, domains, or billing are changed.

  1. Stop new writes and scheduled actions in Asana.
  2. Restore the prior Trello routing, forms, integrations, sending, or sync ownership.
  3. Export the Asana post-cutover delta.
  4. Review and apply safe destination-era changes to Trello.
  5. Run the same blocking checks against the restored source.

Proof to capture: Trello again owns production with current data and no duplicate destination action.

Rollback immediately when
  • Unexplained critical count or value variance
  • Missing or exposed critical data
  • Duplicate production action
  • Failed access, routing, delivery, or integration check
  • A critical feature has no safe destination replacement
08Verification report

Prove the migration worked.

Every blocking check must pass. Capture the evidence before cleanup begins.

0%
Interactive report preview0 / 8 checks passed
PassIDCheckMethodExpected resultEvidence
V-01BlockingWork-item reconciliationCompare counts by project, state, owner, and item type.Every scoped item is accounted for.Count ledger.
V-02BlockingProject and workflow mappingInspect each destination team, project, grouping, and status.All mappings match the signed model.Hierarchy report.
V-03BlockingTask value parityCompare 30 stratified work items.Critical text, fields, dates, and estimates match.Field comparison.
V-04BlockingOwnership and guestsTest active, inactive, internal, and external identities.Assignments and access match policy.User matrix.
V-05BlockingSubtasks and dependenciesQuery representative parent, child, blocked, and related work.No unexplained orphan or flattened critical link.Relationship report.
V-06BlockingAttachment accessOpen representative files as ordinary users.Required files load without source-only access.Attachment log.
V-07BlockingRecurring and connected actionsRun controlled work through every approved rule.One correct destination action with no source duplicate.Automation log.
V-08BlockingSingle work systemInspect source and destination writers and team process.Asana alone owns active work.Cutover checklist.
09Post-migration cleanup

Remove the scaffolding safely.

Safe after: One complete operating cycle, at least seven stable days, and owner sign-off on every blocking check.

  1. Create final Trello exports and archive verification evidence.
  2. Revoke temporary credentials, API keys, webhooks, and elevated roles.
  3. Remove obsolete embeds, forms, jobs, integrations, and DNS records.
  4. Keep the source intact through the approved retention window.
  5. Cancel paid plans only after billing, legal, and recovery review.
  6. Schedule the next Asana backup, access, and migration-playbook review.
Sources and maintenance

Built to be reviewed.

Tested 2026-07-19. Next scheduled review: 2026-10-19.

  1. Asana: import data from other toolsAccessed 2026-07-19
  2. Trello: export dataAccessed 2026-07-19
  3. Asana: CSV importerAccessed 2026-07-19